Highland Park Path Reconstruction Phase 2
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct paths in Highland Park.
Project Notes
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Assigned & Start Date: March 2024
Projected Completion Date:
September 2024
Completion Date:
August 2024
Procurement
Start Date: April 2024
Projected Completion Date:
September 2024
Completion
Date:
August 2024
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Highland Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024