Ocean Parkway Malls and Colonel David Marcus Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the east and west Ocean Parkway Malls from Avenue O to Kings Highway with new asphalt pavement, pipe handrails, trees, benches, signage, greenway markings and curbs; expanded tree pits and restored granite block pavers and a mile marker. This project will also reconstruct the handball and basketball courts, paving, fencing, gates and landscaping and construct a new ADA-accessible drinking fountain in Colonel David Marcus Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Projected Completion Date: December 2012
Completion Date: January 2013

Procurement

Start Date: January 2013
Projected Completion Date: October 2013
Completion Date: December 2013

Construction

Start Date: April 2014
Projected Completion Date: April 2015
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $2,320,000
Funding Source: City Council

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project