Gravesend Park Public Restroom Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new public restroom building at Gravesend Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2012
Projected Completion Date: July 2013
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: August 2015

Construction

Start Date: November 2015
Projected Completion Date: April 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $1,855,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Gravesend Park, Brooklyn
18th Avenue between 56th Street and 57th Street
Community Board: 12

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025