Asser Levy Recreation Center Telecommunication Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will install a new telecommunication service to Asser Levy Recreation Center.

Project Notes

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Assigned & Start Date: April 2024
Projected Completion Date: October 2024
Completion Date: October 2024

Procurement

Start Date: June 2024
Projected Completion Date: November 2024
Completion Date: November 2024

Construction

Start Date: December 2024
Projected Completion Date: February 2025

Understand how we build parks.

Funding

Total Funding: $83,000
Funding Source: Mayoral

Location

Asser Levy Playground, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025