Ocean Parkway Malls Reconstruction, Shore Pkwy to Sea Breeze Ave
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct portions of the west side of the Ocean Parkway Malls.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2011
Projected Completion Date:
August 2012
Completion Date:
September 2012
Procurement
Start Date: September 2012
Projected Completion Date:
June 2013
Completion
Date:
April 2013
Construction
Start Date: May 2013
Projected Completion Date:
May 2014
Completion Date: May 2014
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Ocean Parkway Malls, Brooklyn
Between Shore Parkway and Sea Breeze Avenue
Community Board: 07, 12, 13, 14, 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024