Ocean Parkway Malls Reconstruction, Shore Pkwy to Sea Breeze Ave

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct portions of the west side of the Ocean Parkway Malls.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2011
Projected Completion Date: August 2012
Completion Date: September 2012

Procurement

Start Date: September 2012
Projected Completion Date: June 2013
Completion Date: April 2013

Construction

Start Date: May 2013
Projected Completion Date: May 2014
Completion Date: May 2014

Understand how we build parks.

Funding

Total Funding: $1,251,000
Funding Sources:
  • Borough President
  • City Council

Location

Ocean Parkway Malls, Brooklyn
Between Shore Parkway and Sea Breeze Avenue
Community Board: 07, 12, 13, 14, 15

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project