P.S. 4K Paradise Garden Water Service Installation
-
100% complete
-
100% complete
-
0% complete
This project will install new water service at the P.S. 4K Paradise Garden.
Project Notes
Project Update: A date has been set for construction to begin.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
August 2024
Completion Date:
August 2024
Procurement
Start Date: February 2024
Projected Completion Date:
July 2024
Completion
Date:
August 2024
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: City Council
Last updated: 11/22/2024