George Eagle Carr Community Garden Water Service Installation
-
30% complete
-
40% complete
-
0% complete
This project will install new water service at George Eagle Carr Community Garden.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
June 2025
Procurement
Start Date: February 2024
Projected Completion Date:
July 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Last updated: 11/22/2024