Marine Park Avenue S Parking Lot Reconstruction

  • Design
    90% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the parking lot at Avenue S in Marine Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: November 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: $1,834,000
Funding Source: Mayoral