Alley Pond Park Pathway Reconstruction

  • Design
    90% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct paths in Alley Pond Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: November 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: $1,400,000
Funding Source: City Council

Location

Alley Pond Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project