Coffey Park Multipurpose Play Area Reconstruction

  • Design
    30% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose play area in Coffey Park.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks has received budget approval and is finalizing the work order documentation.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: November 2024

Procurement

Start Date: March 2024
Projected Completion Date: August 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: City Council

Location

Coffey Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024