Clove Lakes Park Pathway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct paths in Clove Lakes Park.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: November 2024
Completion Date: October 2024

Procurement

Start Date: March 2024
Projected Completion Date: August 2024
Completion Date: October 2024

Construction

Start Date: November 2024
Projected Completion Date: November 2025

Understand how we build parks.

Funding

Total Funding: $4,250,000
Funding Source: City Council

Location

Clove Lakes Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025