Washington Market Park Pavement Reconstruction

  • Design
    30% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct a portion of the pavement in Washington Market Park.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

NYC Parks staff members are currently reviewing the scope of the work order.

Project Timeline

Design

Assigned & Start Date: September 2024
Projected Completion Date: October 2024

Procurement

Start Date: October 2024
Projected Completion Date: March 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Washington Market Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024