Faber Park Recreation Center Fire Alarm System Reconstruction
-
80% complete
-
85% complete
-
0% complete
This project will reconstruct the fire alarm system at Faber Park Recreation Center.
Project Notes
Project Update: Parks staff members are reviewing construction documents for this project.
The work order has been sent to the Comptroller's Office for registration.
Project Timeline
Design
Assigned & Start Date: October 2019
Projected Completion Date:
January 2021
Procurement
Start Date: November 2023
Projected Completion Date:
April 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Faber Pool and Park, Staten Island
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 11/22/2024