J. Hood Wright Recreation Center Fire Alarm System Reconstruction
-
80% complete
-
60% complete
-
0% complete
This project will install a new fire alarm system at J. Hood Wright Recreation Center.
Project Notes
Project Update: Parks staff members are reviewing construction documents for this project.
NYC Parks has received budget approval and is finalizing the work order documentation.
Project Timeline
Design
Assigned & Start Date: March 2021
Projected Completion Date:
September 2021
Procurement
Start Date: November 2023
Projected Completion Date:
April 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
J. Hood Wright Park, Manhattan
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 11/22/2024