Orchard Beach in Pelham Bay Park Partial Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct a portion of paths at Orchard Beach in Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: May 2024
Completion Date: April 2024

Procurement

Start Date: July 2023
Projected Completion Date: December 2023
Completion Date: April 2024

Construction

Start Date: November 2024
Projected Completion Date: May 2025

Understand how we build parks.

Funding

Total Funding: $800,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project