Orchard Beach in Pelham Bay Park Partial Path Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct a portion of paths at Orchard Beach in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
May 2024
Completion Date:
April 2024
Procurement
Start Date: July 2023
Projected Completion Date:
December 2023
Completion
Date:
April 2024
Construction
Start Date: November 2024
Projected Completion Date:
May 2025
Understand how we build parks.
Funding
Funding Source: Mayoral