Old Fort #4 Park Basketball Court Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the basketball court at Old Fort #4 Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2023
Projected Completion Date:
May 2024
Completion Date:
April 2024
Procurement
Start Date: July 2023
Projected Completion Date:
December 2023
Completion
Date:
April 2024
Construction
Start Date: September 2024
Projected Completion Date:
April 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Washington's Walk, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024