Corporal Thompson Park West Brighton Pool Deck Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the deck of the West Brighton Pool in Corporal Thompson Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2023
Projected Completion Date: November 2023
Completion Date: October 2023

Procurement

Start Date: May 2023
Projected Completion Date: October 2023
Completion Date: October 2023

Construction

Start Date: September 2023
Projected Completion Date: May 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

CPL. Thompson Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025