Sheltering Arms Pool Deck Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the deck at Sheltering Arms Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2023
Projected Completion Date:
November 2023
Completion Date:
October 2023
Procurement
Start Date: May 2023
Projected Completion Date:
October 2023
Completion
Date:
October 2023
Construction
Start Date: October 2023
Projected Completion Date:
June 2024
Completion Date: April 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Sheltering Arms Playground, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024