Kissena Park Boat House Roof Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the roof at the Kissena Boat House.
Project Notes
Project Update: A date has been set for construction to begin.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2023
Projected Completion Date:
August 2024
Completion Date:
January 2025
Procurement
Start Date: December 2023
Projected Completion Date:
May 2024
Completion
Date:
June 2024
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Kissena Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025