Sunset Park Spray Shower Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will demolish the existing wading pool and construct a spray shower and plaza in Sunset Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2010
Projected Completion Date: May 2012
Completion Date: June 2012

Procurement

Start Date: June 2012
Projected Completion Date: March 2013
Completion Date: May 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: October 2014

Understand how we build parks.

Funding

Total Funding: $1,130,000
Funding Sources:
  • City Council
  • Mayoral

Location

Sunset Park, Brooklyn
7th Avenue between 41st Street and 44th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025