Kissena Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct paths in Kissena Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2023
Projected Completion Date: October 2024
Completion Date: August 2024

Procurement

Start Date: April 2024
Projected Completion Date: September 2024
Completion Date: August 2024

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $1,100,000
Funding Source: Mayoral

Location

Kissena Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024