Crocheron Park Path Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct paths in Crocheron Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2022
Projected Completion Date:
October 2024
Completion Date:
August 2024
Procurement
Start Date: April 2024
Projected Completion Date:
September 2024
Completion
Date:
August 2024
Construction
Start Date:
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Crocheron Park, Queens