Amsterdam Avenue and 126th Street Greenstreet Fence Installation

  • Design
    30% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will install a fence at the Amsterdam Avenue and 126th Street Greenstreet.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

The budget approval documents are currently under review by the NYC Office of Management and Budget.

Project Timeline

Design

Assigned & Start Date: May 2024
Projected Completion Date: November 2024

Procurement

Start Date: July 2024
Projected Completion Date: December 2024

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024