Amsterdam Avenue and 126th Street Greenstreet Fence Installation
-
30% complete
-
40% complete
-
0% complete
This project will install a fence at the Amsterdam Avenue and 126th Street Greenstreet.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: May 2024
Projected Completion Date:
November 2024
Procurement
Start Date: July 2024
Projected Completion Date:
December 2024
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024