Crotona Park Nature Center Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the roof at the Crotona Park Nature Center.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2023
Projected Completion Date: August 2024
Completion Date: August 2024

Procurement

Start Date: December 2023
Projected Completion Date: May 2024
Completion Date: June 2024

Construction

Start Date:

Understand how we build parks.

Funding

Total Funding: $700,000
Funding Source: Mayoral

Location

Crotona Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024