Lozada Playground Public Restroom Building Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the public restroom building in Lozada Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2022
Projected Completion Date: October 2023
Completion Date: November 2023

Procurement

Start Date: January 2023
Projected Completion Date: June 2023
Completion Date: September 2023

Construction

Start Date: January 2024
Projected Completion Date: April 2024
Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $89,000
Funding Source: Mayoral

Location

Lozada Playground, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024