Highland Park Ballfields 1 & 2 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct natural turf ballfields 1 and 2 in Highland Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2010
Projected Completion Date: February 2013
Completion Date: June 2013

Procurement

Start Date: June 2013
Projected Completion Date: March 2014
Completion Date: October 2014

Construction

Start Date: November 2014
Projected Completion Date: May 2016
Completion Date: May 2016

Understand how we build parks.

Funding

Total Funding: $2,758,000
Funding Sources:
  • City Council
  • Mayoral

Location

Highland Park, Queens
Jamaica Avenue between Linwood Street and Shepherd Avenue
Community Board: 05, 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024