Red Hook Pool Tub Expansion Joint Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the pool tub expansion joints at Red Hook Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: March 2023
Completion Date: February 2023

Procurement

Start Date: October 2022
Projected Completion Date: March 2023
Completion Date: January 2023

Construction

Start Date: January 2023
Projected Completion Date: June 2023
Completion Date: May 2023

Understand how we build parks.

Funding

Total Funding: $700,000
Funding Source: Mayoral

Location

Red Hook Recreation Area, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025