Hero Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct paths in Hero Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: June 2023
Completion Date: November 2022

Procurement

Start Date: October 2022
Projected Completion Date: March 2023
Completion Date: November 2022

Construction

Start Date: April 2024
Projected Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $195,000
Funding Source: Mayoral

Location

Hero Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024