Walt Whitman Park Sewer Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the sewer at Walt Whitman Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2023
Projected Completion Date: August 2024
Completion Date: August 2024

Procurement

Start Date: February 2024
Projected Completion Date: July 2024
Completion Date: August 2024

Construction

Start Date: September 2024
Projected Completion Date: December 2024

Understand how we build parks.

Funding

Total Funding: $1,295,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Walt Whitman Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024