Marcus Garvey Park Path Reconstruction and Ramps Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct a portion of the path and construct ramps in Marcus Garvey Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: June 2024
Completion Date: May 2024

Procurement

Start Date: July 2023
Projected Completion Date: December 2023
Completion Date: October 2023

Construction

Start Date: April 2024
Projected Completion Date: April 2025

Understand how we build parks.

Funding

Total Funding: $4,400,000
Funding Source: Mayoral