John Jay Park Ramp Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an ADA compliant ramp in John Jay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2023
Projected Completion Date: July 2024
Completion Date: May 2024

Procurement

Start Date: July 2023
Projected Completion Date: December 2023
Completion Date: October 2023

Construction

Start Date: November 2023
Projected Completion Date: July 2024
Completion Date: June 2024

Understand how we build parks.

Funding

Total Funding: $998,000
Funding Source: City Council

Location

John Jay Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024