Wakefield Playground Public Restroom Building Reconstruction
-
30% complete
-
40% complete
-
0% complete
This project will reconstruct the public restroom building at Wakefield Playground.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
The budget approval documents are currently under review by the NYC Office of Management and Budget.
Project Timeline
Design
Assigned & Start Date: August 2024
Projected Completion Date:
January 2025
Procurement
Start Date: October 2024
Projected Completion Date:
March 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Wakefield Playground, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024