Pelham Bay Park Synthetic Turf and Track Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field and track at Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2023
Projected Completion Date: September 2024
Completion Date: April 2024

Procurement

Start Date: September 2023
Projected Completion Date: February 2024
Completion Date: April 2024

Construction

Start Date: March 2024
Projected Completion Date: December 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $3,290,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024