Pelham Bay Park Synthetic Turf and Track Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field and track at Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2023
Projected Completion Date:
September 2024
Completion Date:
April 2024
Procurement
Start Date: September 2023
Projected Completion Date:
February 2024
Completion
Date:
April 2024
Construction
Start Date: March 2024
Projected Completion Date:
December 2024
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025