Chelsea Park Synthetic Turf and Track Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field and track at Chelsea Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2022
Projected Completion Date: April 2023
Completion Date: January 2023

Procurement

Start Date: September 2022
Projected Completion Date: February 2023
Completion Date: December 2022

Construction

Start Date: April 2023
Projected Completion Date: December 2023
Completion Date: September 2023

Understand how we build parks.

Funding

Total Funding: $1,250,000
Funding Sources:
  • Mayoral
  • City Council

Location

Chelsea Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024