Saratoga Park Memorial Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will restore the war memorial in Saratoga Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2010
Completion Date:
September 2011
Procurement
Start Date: September 2011
Projected Completion Date:
June 2012
Completion
Date:
May 2013
Construction
Start Date: September 2013
Projected Completion Date:
September 2014
Completion Date: August 2014
Understand how we build parks.
Funding
Funding Source: City Council
Location
Saratoga Park, Brooklyn
Macon Street, Howard Ave, Halsey Street and Saratoga Avenue
Community Board: 03
Project Staff
Project Liaison: Davey Ives