Saratoga Park Memorial Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will restore the war memorial in Saratoga Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2010
Completion Date: September 2011

Procurement

Start Date: September 2011
Projected Completion Date: June 2012
Completion Date: May 2013

Construction

Start Date: September 2013
Projected Completion Date: September 2014
Completion Date: August 2014

Understand how we build parks.

Funding

Total Funding: $216,000
Funding Source: City Council

Location

Saratoga Park, Brooklyn
Macon Street, Howard Ave, Halsey Street and Saratoga Avenue
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project