Lemon Creek Park Seguine Mansion Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the Seguine Mansion in Lemon Creek Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2022
Projected Completion Date: October 2023
Completion Date: November 2023

Procurement

Start Date: August 2022
Projected Completion Date: December 2022
Completion Date: September 2023

Construction

Start Date: July 2023
Projected Completion Date: November 2023
Completion Date: November 2023

Understand how we build parks.

Funding

Total Funding: $158,000
Funding Source: Mayoral

Location

Lemon Creek Park, Staten Island

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project