Fort Totten Pool Main Drain Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the main drain at Fort Totten Pool.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2022
Projected Completion Date:
September 2022
Completion Date:
December 2022
Procurement
Start Date: August 2022
Projected Completion Date:
January 2023
Completion
Date:
July 2022
Construction
Start Date: June 2022
Projected Completion Date:
July 2023
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Fort Totten Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025