Big Bush Playground Synthetic Turf Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf field at Big Bush Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2022
Projected Completion Date: October 2023
Completion Date: June 2023

Procurement

Start Date: October 2022
Projected Completion Date: March 2023
Completion Date: June 2023

Construction

Start Date: June 2023
Projected Completion Date: November 2023
Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $770,000
Funding Source: Mayoral

Location

Big Bush Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024