Big Bush Playground Synthetic Turf Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the synthetic turf field at Big Bush Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2022
Projected Completion Date:
October 2023
Completion Date:
June 2023
Procurement
Start Date: October 2022
Projected Completion Date:
March 2023
Completion
Date:
June 2023
Construction
Start Date: June 2023
Projected Completion Date:
November 2023
Completion Date: August 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Big Bush Playground, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024