Wards Island Park Synthetic Turf Maintenance Yard Curb Construction
-
100% complete
-
100% complete
-
100% complete
This project will install a curb at the synthetic turf maintenance yard in Wards Island Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2022
Projected Completion Date:
October 2022
Completion Date:
June 2022
Procurement
Start Date: May 2022
Projected Completion Date:
October 2022
Completion
Date:
July 2022
Construction
Start Date: June 2022
Projected Completion Date:
June 2022
Completion Date: June 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Wards Island Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025