Chelsea Recreation Center Storefront Entry System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the storefront entry system at the Chelsea Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2022
Projected Completion Date:
November 2022
Completion Date:
June 2022
Procurement
Start Date: May 2022
Projected Completion Date:
October 2022
Completion
Date:
May 2022
Construction
Start Date: March 2023
Projected Completion Date:
December 2023
Completion Date: September 2023
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Chelsea Recreation Center, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024