Fort Greene Park Willoughby Avenue Entrance Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the Willoughby Avenue entrance, park paths, perimeter sidewalks and landscape elements in Fort Greene Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2010
Projected Completion Date:
December 2011
Completion Date:
December 2013
Procurement
Start Date: December 2013
Projected Completion Date:
September 2014
Completion
Date:
June 2014
Construction
Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date: December 2015
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Fort Greene Park, Brooklyn
Willoughby Avenue and Washington Park
Community Board: 02
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project