Fort Greene Park Willoughby Avenue Entrance Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the Willoughby Avenue entrance, park paths, perimeter sidewalks and landscape elements in Fort Greene Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2010
Projected Completion Date: December 2011
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: June 2014

Construction

Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: December 2015

Understand how we build parks.

Funding

Total Funding: $1,567,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Fort Greene Park, Brooklyn
Willoughby Avenue and Washington Park
Community Board: 02

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024