Upper Highland Park Playground Public Restroom Building Sewer Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sewer line of the public restroom building in Upper Highland Park Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2022
Projected Completion Date:
September 2022
Completion Date:
July 2022
Procurement
Start Date: January 2022
Projected Completion Date:
June 2022
Completion
Date:
July 2022
Construction
Start Date: October 2022
Projected Completion Date:
February 2023
Completion Date: December 2022
Understand how we build parks.
Funding
Funding Source: City Council
Location
Highland Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025