Betsy Head Park Pool Filter Plant Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct a portion of the filter plant in Betsy Head Pool.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: September 2022
Completion Date: May 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022
Completion Date: April 2022

Construction

Start Date: September 2022
Projected Completion Date: February 2023
Completion Date: November 2022

Understand how we build parks.

Funding

Total Funding: $225,000
Funding Source: Mayoral

Location

Betsy Head Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024