Howard Playground Howard Pool Tunnel Wall Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the tunnel wall of Howard Pool in Howard Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2021
Projected Completion Date:
May 2022
Completion Date:
March 2022
Procurement
Start Date: December 2021
Projected Completion Date:
May 2022
Completion
Date:
June 2022
Construction
Start Date: April 2022
Projected Completion Date:
May 2022
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Howard Playground, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024