Howard Playground Howard Pool Tunnel Wall Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the tunnel wall of Howard Pool in Howard Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2021
Projected Completion Date: May 2022
Completion Date: March 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022
Completion Date: June 2022

Construction

Start Date: April 2022
Projected Completion Date: May 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $108,000
Funding Source: Mayoral

Location

Howard Playground, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024