North 5th Street Pier and Park Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct pavement at North 5th Street Pier and Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: December 2021

Procurement

Start Date: October 2021
Projected Completion Date: March 2022
Completion Date: March 2022

Construction

Start Date: November 2021
Projected Completion Date: February 2022
Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $272,000
Funding Source: Private

Location

North 5th Street Pier and Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024