North 5th Street Pier and Park Pavement Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct pavement at North 5th Street Pier and Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2021
Projected Completion Date:
June 2022
Completion Date:
December 2021
Procurement
Start Date: October 2021
Projected Completion Date:
March 2022
Completion
Date:
March 2022
Construction
Start Date: November 2021
Projected Completion Date:
February 2022
Completion Date: April 2022
Understand how we build parks.
Funding
Funding Source: Private
Location
North 5th Street Pier and Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks