General Hart Playground Public Restroom Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof of the public restroom building in General Hart Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2021
Projected Completion Date: September 2022
Completion Date: July 2022

Procurement

Start Date: December 2021
Projected Completion Date: May 2022
Completion Date: June 2022

Construction

Start Date: December 2022
Projected Completion Date: April 2023
Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

General Hart Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024