Alley Pond Park Telecommunication Lines Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the telecommunication lines at Alley Pond Park.

Project Timeline

Design

Assigned & Start Date: October 2021
Projected Completion Date: May 2022
Completion Date: May 2022

Procurement

Start Date: November 2021
Projected Completion Date: April 2022
Completion Date: May 2022

Construction

Start Date: May 2022
Projected Completion Date: October 2022
Completion Date: October 2022

Understand how we build parks.

Funding

Total Funding: $180,000
Funding Source: Mayoral

Location

Alley Pond Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024