Van Cortlandt House Museum and Van Cortlandt Park Nature Center Telecommunication Lines Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the telecommunication lines at the Van Cortlandt House Museum and Van Cortlandt Park Nature Center.
Project Timeline
Design
Assigned & Start Date: October 2021
Projected Completion Date:
May 2022
Completion Date:
May 2022
Procurement
Start Date: November 2021
Projected Completion Date:
April 2022
Completion
Date:
May 2022
Construction
Start Date: May 2022
Projected Completion Date:
August 2022
Completion Date: August 2022
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Van Cortlandt Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos