Mullaly Park Telecommunication Lines Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the telecommunication lines at Mullaly Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2021
Projected Completion Date: May 2022
Completion Date: May 2022

Procurement

Start Date: October 2021
Projected Completion Date: March 2022
Completion Date: May 2022

Construction

Start Date: May 2022
Projected Completion Date: September 2022
Completion Date: September 2022

Understand how we build parks.

Funding

Total Funding: $80,000
Funding Source: Mayoral

Location

Rev. T. Wendell Foster Park and Recreation Center , Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project