East River Esplanade Pavement Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct sections of pavement along the East River Esplanade between East 100th Street and East 101st Street and at East 107th Street.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2021
Projected Completion Date: July 2022
Completion Date: November 2021

Procurement

Start Date: August 2021
Projected Completion Date: January 2022
Completion Date: October 2021

Construction

Start Date: December 2021
Projected Completion Date: December 2022
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $160,000
Funding Source: Mayoral

Location

East River Esplanade, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024